Jump to content
Baseops Forums
Sign in to follow this  
HuggyU2

Contracting: GPC and sole-source

Recommended Posts

Posted (edited)

For you Contracting experts:

1.  What's the max you can put on a GPC?  It was $2500, but I heard it went up to $5000.  True?

2.  If the AF wants to go sole-source on a contract without competing it, what's the most they can spend?  I"m assuming it's the same as the GPC card limit ($2500 or $5000).  

Edited by HuggyU2

Share this post


Link to post
Share on other sites

You can sole source well above the gpc limit. You just have to be able to provide sufficient justification to make it through all the contracting and legal wickets. I'm working on trying to sole source a nearly $300k purchase. 

  • Thanks 1

Share this post


Link to post
Share on other sites

Also.. GPC limit is pretty high now, $20K?

at LRAFB, we are supposed to be getting a “super GPC” (held by the Group RAs) that is supposed to have a crazy high limit.. $200+K. They say it’ll be here by FY20

Share this post


Link to post
Share on other sites

GPC limit is $25k, but I believe they have to get an authorization from finance or contracting to go above $5k, which is the limit before you have to go through contracting and do the three competing vendors shuffle. This is subject to change based on my memory.

Sent from my SM-N960U1 using Tapatalk

Share this post


Link to post
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.
Note: Your post will require moderator approval before it will be visible.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

Sign in to follow this  



×
×
  • Create New...